Episcopal Church of the Ascension Visioning and Master Plan - Presented November 4th, 2018

Size: px
Start display at page:

Download "Episcopal Church of the Ascension Visioning and Master Plan - Presented November 4th, 2018"

Transcription

1 Episcopal Church of the Ascension Visioning and Master Plan - Presented November 4th, 2018 Prepared for: Episcopal Church of the Ascension, Stillwater, Minnesota Prepared By: Kodet Architectural Group Ltd, Minneapolis, Minnesota Architect s Job Number:

2 Contents Acknowledgments i Contents ii Executive Summary 1-4 Existing Conditions Assessment 5-14 Community Engagement Plan Acknowledgments Ascension Visioning Team: Rev. Buff Grace, Monica Davis, Jim Caldwell, Lauren Hannigan, Erik Sorensen Ascension Clergy and Staff: Rev. Marilyn Baldwin, Brenda Hoffman, Nancy Whipkey, Ruth Meyer, Mindy Boynton, Ascension Discovery Team: Linda Amrein, Duane Arndt, Kathy Carlson, Jim Christopherson, Mark Doneux, Don Greeley, Tom History and Preservation Visioning and Master Plan Next Steps and Resources Marie Goebel, Edmund Farnham Mcelin, Nance Purcell i ii

3 Executive Summary Executive Summary Background Worship Space Renovation The Presenting Concern Since 2010, Vestry and other leaders have been concerned about how worn the carpet in the nave is. Besides the aesthetic issues, wrinkles in the carpet have caused some to fall. Repairs were made in 2011, but the company making the repairs did not guarantee the repair, and with each year concern grows that the carpet will fail quickly. The carpet needs to be replaced. Maintenance Requirement When the carpet is replaced, the pews will have to be removed in order to lay the new carpet, and the church has been advised by parishioners knowledgeable about furniture that moving the old pews is likely to require significant repair to them. This means that, at a minimum, there will be significant expense to simply maintain the worship space just as it is. The Opportunity Given that Ascension is faced with a significant maintenance expense and the upheaval of the church to accomplish that maintenance, this is the perfect time to ask if there are other renovations that could make the worship even more expressive of God s love and make it more accessible to more people. Asking these questions now is faithful stewardship. Ascension Interior circa 1946 Published in Centennial Observance Pamphlet, June 7, 1946 The Episcopal Church of the Ascension, now located at 214 3rd Street North in Stillwater, Minnesota, dates to 1838 when Ezekiel Gear, chaplain from Ft. Snelling, conducted the first Episcopal service in the wilderness that was to become Stillwater. Regular services began in 1846 and construction for a church to be known as Ascension began in 1851, at Second Street just 1 north of today s Lowell Inn. A newer church was consecrated at the present Ascension site in That church, regrettably, was struck by lightning and burned to the ground immediately following a restoration project in A new red brick building in the Mid-Victorian style was dedicated exactly one year later in years later that building still serves the Ascension congregation. Stillwater, Minnesota, looking south on Third Street in Collected by John Runk, photographer, Stillwater, MN Initial Process Visioning and Master Plan Draft Ascension s Vestry understands how central worship is to the Ascension community and how important the current worship space is to our experience. For this reason, a process was developed to gather input and to engage members with specific knowledge that can assist the process, and to employ professionals who can honor the needs of a modern community in an historic church building. May 2018 The Vestry invited anyone who wanted to serve on a Discovery Team to apply. This Discovery Team, including the vestry leadership for the master plan, would visit other places of worship throughout the summer to gather ideas and combine those ideas with a review of Ascension s space. Their findings were reported to the parish in September, This Team continued to be part of the process through the end of the master plan process. June 2018 The Vestry leadership interviewed architectural firms for the purpose of conducting engagement with the congregation and to develop a visioning and master plan for possible renovation. The scope of this project did not include going forward with actual physical changes to the building. From this process Kodet Architectural Group was recommended to the Vestry for Approval. Visioning and Master Plan Draft

4 Executive Summary Executive Summary Visioning and Master Plan Summary Prior to the kickoff meeting on August 14th, 2018, Kodet collaborated with the Visioning Team to develop a work plan for this project. At its essence, this work plan consists of the following three components: an Existing Conditions Assessment of the Worship Space, the development and implementation of a Community Engagement plan, and the compiling of this information (along with 3 design options) into a Master Plan and Visioning document for the Episcopal Church of the Ascension. The physical area that was to be the focus of this study was determined to be the Worship Space (Sanctuary, Narthex, etc) as well as entry/exit points of the Worship Space. Existing Conditions Assessment The Existing Conditions Assessment includes review of existing documentation, on-site field verification, and an accessibility assessment of the Worship Space (Sanctuary, Narthex, etc) as well as entry/exit points of the Worship Space. Existing Conditions Verification Kodet conducted the following to review the existing conditions: Review of existing drawing sets made available by the Church. One field verification site to refine existing Worship Space floor plans and photo document existing conditions. 3 Accessibility Narrative In addition to a current set of floor plans and photo documentation, an Accessibility Narrative of the Worship Space and its entry/exit points will be included. Possible corrections for improved accessibility will be addressed as part of the design options later in this Master Plan. The intent of this narrative is to document existing conditions. Community Engagement Visioning and Master Plan Draft Community Engagement for this project was composed of meetings with the congregation, Discovery Team & Staff/Worship focus groups, and the collection of congregation/community feedback via survey and direct feedback to Visioning Team. The development of the Community Engagement plan was a collaborative effort between the Visioning team and Kodet. Visioning Team Buff Grace Rector Monica Davis Sr. Warden Jim Caldwell Vestry 2019 Lauren Hannigan Vestry 2020 Erik Sorensen Vestry 2021 Visioning and Master Plan Clergy and Staff Marilyn Baldwin Associate Priest Brenda Hoffman Deacon Nancy Whipkey Director of Music Ruth Meyer Asst. Director of Music Mindy Boynton Youth Ministry Marie Goebel Office Administration Edmund Farnham Custodian Discovery Team Linda Amrein Duane Arndt Kathy Carlson Jim Christopherson Mark Doneux Don Greeley Tom Mcelin Nance Purcell Drawing from the outcome of the community engagement, existing conditions and accessibility narrative, Kodet developed 3 concepts reflecting Minimum, Medium, and Maximum levels of intervention. These concepts took shape early on in the process and were developed and reviewed at project meetings in collaboration with the Visioning Team. Time-line The Visioning and Master Plan project began with a Kick-Off meeting with the Visioning Team on August 14th, 2018 and concluded with a final presentation to the congregation on Sunday November 4th, In addition to the meetings illustrated to the right, Kodet and the Visioning team conducted progress meetings, conference calls, and reviews via . Visioning and Master Plan Draft

5 Existing Conditions Assessment Existing Conditions Assessment Episcopal Church of the Ascension Visioning and Master Plan - Presented November 4th, 2018 Episcopal Church of the Ascension Visioning and Master Plan - Presented November 4th, 2018 Ascension Site Plan Site Entry and Accessibility Description Description The Episcopal Church of the Ascension is located The congregation enters the church from both 3rd at 214 3rd Street North in Stillwater, Minnesota. Street North and 4th Street North. Wheelchair Adjacent properties are the Stillwater Public Library accessible entry to the church occurs off of 3rd to the north, Stillwater City Hall to the West, Street primarily through the lower level entry of and the Stillwater Water Department along with the fellowship hall where an elevator provides Trinity Lutheran Church to the south. The church access to the sanctuary. Limited accessible parking is located on a hill with significant grade change is available off street in the north side driveway, in each direction. The church s property spans where an exterior path around the sanctuary leads between 4th Street North and 3rd Street North to an accessible entrance to the fellowship hall at with the primary address being on 3rd Street North. the level of the Sanctuary. The sanctuary is only Parking needs are met through street parking and accessible by wheelchair from the gallery and not shared lots in the surrounding neighborhood. through the traditional front entrance/narthex. Note: Complete and measured architectural drawings are not included in the contents of the assessment. The included diagrams identifies primary locations referenced in this document and is intended to be used for reference only. Stillwater Public Library rd Street North 5 Stillwater Water Department rd Street North Trinity Lutheran Church th Street North (3rd Street Entry) Visioning and Master Plan Draft Address 15 Groveland Terrace Contact Stillwater City Hall th Street North P: F: arch@kodet.com Primary stair entry at 3rd Street North Wheelchair accessible entry to lower level fellowship hall off 3rd Street North Visioning and Master Plan Draft Address 15 Groveland Terrace Contact Wheelchair accessible parking located at north driveway adjacent to sanctuary. P: F: arch@kodet.com 6

6 Existing Conditions Assessment Existing Conditions Assessment Entry and Circulation at Gallery Description The gallery is the focal point of circulation within the church and is the primary point of access to the sanctuary for much of the congregation. A stair and elevator bring congregation members from the lower level of the building and from the lower level 3rd Street entrance. An entry vestibule off of 3rd Street at the main level brings congregation members into the gallery adjacent to the Chapel. Congregation members entering from 4th Street arrive through an internal hallway past the Dining/ Multi-purpose space into the gallery. A single set of doors provides access to the worship space adjacent to the chancel/altar. Entry and Circulation at Narthex Description The traditional entry to the sanctuary, the narthex serves as entrance for congregation members parking along 3rd Street North. Additionally a small stair at the base of the bell tower allows for circulation to the basement, primarily used by clergy and choir members for services. Along with entry, welcoming, and circulation the Narthex is utilized for storage of coats, name-tags, and other worship items. The Narthex is an internally focused space with solid entry doors and opaque stained glass windows. Single door vestibule entrance to gallery. Narthex looking north. 7 Hallway from west/4th Street North entrance to gallery. Stair and elevator entry from lower level fellowship hall to gallery. Visioning and Master Plan Draft Congregation name tag board Guest sign in table and storage. Visioning and Master Plan Draft

7 Existing Conditions Assessment Existing Conditions Assessment Nave Description The Nave is traditionally laid out with wood pews and stained glass windows at the sides and rear walls. The pews allow for an approximate seating capacity of 230 people per initial code review. The wood pews are upholstered and have kneelers which are used in the service. The choir, clergy and congregation process via the center isle, which is noted to be tight for special services, to the chancel and altar during services. Two side isles accommodate circulation before and after services. The baptismal font is located at the rear of the nave, where the bell choir and other functions also occur depending on liturgical requirements. Chancel, Altar, and Organ Description During services the chancel seats clergy, attendees, and the choir. The congregation processes up three stairs onto the chancel and through a narrow path between the choir to reach the altar for communion where clergy and a number of attendees serve communion at a traditional rail. Congregation members seated to the north of the nave exit the altar through a narrow path behind the organ which requires ducking to avoid the organ. The chancel is unable to accommodate the church s piano or other musical assembles during services. The sacristy is accessed to the left of the altar at the rear of the worship space. Baptismal Font at rear of nave Nave looking east towards 3rd Street Rear of Nave Piano, lectern, and choir seating at front of chancel Altar with traditional communion rails at rear of chancel Pulpit, choir seating and organ at chancel 9 Visioning and Master Plan Draft Visioning and Master Plan Draft

8 Existing Conditions Assessment Existing Conditions Assessment Accessibility Narrative Synopsis The Episcopal Church of the Ascension, located in Stillwater, MN, is a two-story facility with classrooms, choir staging, storage and restrooms in the lower level. On the main level, a fellowship addition was added in the 1920s to the original 1888 historic sanctuary. Renovations in 2000 to the fellowship addition updated the facilities and incorporated an elevator for wheelchair access from the lower level 3rd Street North entry to worship space on the main level. Other functions on the main level include meeting rooms, a chapel, the kitchen, and parish hall. The purpose of this accessibility narrative is to review the accessibility compliance of the building for both the public and staff. The facility was reviewed with regard to both the MN State Accessibility Code, Chapter 1341 (2015) and the Americans with Disabilities Act (2010) and their related documents. This accessibility narrative focuses on the worship area and the main function areas that are part of worship at the Church, including the worship space, parish hall and main level restrooms. The narrative 11 includes the access to the facility from 3rd Street N. From brief observations of the space and an analysis of the existing plans, it has been found that there are several components to the worship area that do not meet the accessibility code. The following narrative will prioritize accessibility as follows: Approach and Entrance Accessible Path Through Building Restrooms Parking Drinking Fountains Additional Items * Note that the narrative is not fully inclusive - it is a preliminary and representational summary of the major functions of the Church, including the worship space, main level restrooms, and Parish Hall. * Note that Episcopal Church of the Ascension is not listed as an historic building on a national, state, or local Register. It is, however, part of the Downtown Stillwater Design Review District, as well as the potential Stillwater Cultural Landscape District. Building changes would need to be reviewed by the City. Since the building is not listed on a Register, accessible upgrades would be required with changes to the building. Priority 1 Parking/Drop-off There is not currently a compliant accessible parking space. The parking space located on the driveway could be upgraded to be compliant. Slope and cross slope of the space should be verified and appropriate striping for the parking space and access aisle should be added. The sign location should also be brought to code, as it is not installed at the correct height. The curb cuts and accessible parking at the front of the building on 3rd Street N. are not dedicated to the Episcopal Church of the Ascension, but they do provide the on-grade access point to the lower level. The recommendation would be to work with the City and community (neighbors, etc.) to create a designated drop-off from the street. Approach Entry into the facility occurs from several different locations on two streets, 3rd Street N. and 4th Street N. This narrative did not evaluate the approach and entrance from 4th Street N., as the only path from the street to the building includes stairs. Additionally, the worship area is closest to 3rd Accessibility Narrative Street North. Visioning and Master Plan Draft There are two levels of entry from 3rd Street North, allowing access to the main and lower floors, depending on where the approach begins. From the parking space by the driveway, there is a sloped sidewalk that leads to the main level. From the city sidewalk there is a clear and accessible sidewalk to the lower level. The sidewalks are currently in fair condition and appear to meet the required slope measurements for an accessible path. The sidewalks should be monitored so that they remain in compliance, and there should be no changes in level greater than 1/4 high. If they do exist, the sidewalk should be ground down or otherwise modified to comply. Heaving and cracking are examples of conditions that should be monitored, given the site location and Minnesota winters. Direct entry into the narthex is by two sets of stairs in the north and south of the space. From the city sidewalk there is a set of stairs, then an additional sidewalk and another set of stairs that lead to the narthex. There are several items with the stairs that are not in compliance, such as unequal tread depth, non-compliant handrails, and lack of a visual contrast at the edge of the tread surface. Adding strips of visual contrast at the leading two inches of the tread would be easily achievable. Changes to the concrete steps and handrails would be a more major undertaking. Entrance The entry at the lower level, which is approached from the city sidewalk, is accessible; but needs signage indicating as such. The main level entry, accessed from the parking spot in the driveway, is not fully accessible due to missing latch-side clearance at the door. In the entry vestibule, the door to the chapel creates overlapping door swings. The chapel door has a vision panel that does not meet accessibility codes because of its location in the door. It is too high, (above the required maximum starting point of 48 ), thereby prohibiting accessible visible access to the vision panel. A vision panel is not required on the door, but since it is provided it should be accessible. Door hardware at each of the entries off of 3rd Street that can be accessed by a ramp should be upgraded to meet code, by switching the knobs to levers. Each space needs a minimum of one path of accessible entry, and hardware upgrades would not be required at every door if one path was provided. Further analysis of each space and hardware would help to determine which spaces need to change, and which could keep more historic hardware. Visioning and Master Plan Draft

9 Existing Conditions Assessment Existing Conditions Assessment Accessibility Assessment Priority 2 Access to Goods and Services Once inside the building, there is an accessible path to the worship space. From the lower level, one would move through the vestibule to access the elevator. The elevator brings one to the main level, where there is a direct path to the worship, parish hall, and restrooms. The path to the worship space is accessible, but there are overlapping door swing areas in the hallway leading into the parish hall from the gallery and the storage room by the stairs. These door swings would need to be addressed to make the parish hall accessible. From the main level, the vestibule is inaccessible due to lack of latch side clearance at the doors. Once in the gallery, the worship area is accessible. However, the parish hall and restrooms have the same door swing clearance issue as listed above. Nave Seating There is not currently adequate accessible seating in the worship area. This does not comply for the following reasons: the number of accessible seats does not meet the required number and there is an inadequate number of companion seats. 13 The worship seating currently holds approximately 230 people. According to code, five accessible seats are required. Each accessible seat is also required to have one companion seat that is equivalent in size, quality, comfort and amenities to the immediate area. Depending on the calculations, there are either four available accessible seats and only two companion seats, or two accessible seats, each with a companion seat. The accessible seating is to be equally dispersed throughout the seating area. According to the code, there are two locations required for seating dispersion. At this time, the accessible seating is at the back or front of the church, which meets the minimum code requirement of two different locations. The appropriate number of accessible seats and companion seats should be added. Though not required by code, accessible seating dispersion that includes a space in the middle of the worship area is desirable. Nave, Chancel, and Altar The chancel is positioned three steps higher than the nave and is only accessible by stairs. The choir seating and organ are located on the chancel. The chancel also holds the pulpit and lecterns for service. These spaces are not accessible for the members of the clergy, musicians, or any other public members of the church who may be aiding in a service. This could be members who are readers, or people helping with communion. This is a high priority item. Adding a ramp or lift would be the recommendation to access the space, which would be a significant change. The altar is an additional two steps higher than the chancel. During the service, communion takes place at the altar. This is prohibitive to those with physical disabilities due to the steps and inaccessible path of travel after receiving communion, but a program change moving the communion location may be the easiest way to solve this issue. Accessibility Assessment Visioning and Master Plan Draft Narthex The narthex is an inaccessible location from both the exterior and the nave. Entry from the exterior was previously discussed. For entry from the worship space, the double doors are under five feet wide total, thus the individual door width is less than the 32 required. Welcoming items such as the guest book, church information, and member name tags are all located in the narthex. By moving these items to a different, accessible location, these programmatic functions could become accessible and changes to the narthex would not be needed. Additional Items As a general note, hardware throughout the church could be made accessible. Much of the hardware is currently accessible, so changing any remaining knobs to levers would benefit the accessibility of the Church with minimal investment. Each space needs a minimum of one path of accessible entry. Accessories throughout the Church, such as light switches and room signs, are to be located no more than four feet high. If some of the accessory items, such as thermostat controls, could be controlled only by staff and not used as public features, that could mean that the accessories would not need to change immediately. CONCLUSION Overall, access into the building and throughout the path of travel to the worship space is accessible. Though the paths are not the most direct, given the historic nature of the building and the topography of the site, the approach should not need to drastically change. Minor improvements to signage and hardware should be addressed. Changing the hardware is a priority item than some of the other issues, but it is readily achievable without a big investment. Within the worship space, the accessible seating could be improved. The changes to the flooring material would provide the opportunity to make those changes. Modifications to the location of communion and/or the program location could make communion more accessible to all. Visioning and Master Plan Draft

10 Community Engagement Plan Community Engagement Plan Focus Group Feedback Discovery Team Feedback Kodet engaged Ascension Clergy and Staff through surveys and a Focus Group meeting at the church conducted on August 28th, An additional conference call was held for the musical staff, Nancy Whipkey and Ruth Meyer, who were unable to attend the initial meeting. The surveys content was In May 2018, the Vestry invited anyone who wanted to serve on a Discovery Team to apply. This Discovery Team, including the vestry leadership for the renovation, visited other places of worship (listed below) throughout the summer to gather ideas and combined those ideas with a review of Ascension s own space. These findings were reported to the parish in the September 2018 Congregation Meeting. Kodet engaged with the Discovery Team through a survey and meeting on August 28th, Discovery Team Linda Amrein Duane Arndt Kathy Carlson Jim Christopherson Mark Doneux Don Greeley Tom Mcelin Nance Purcell generated by Kodet with input from the Visioning Team to engage the specific programmatic needs of the clergy and staff. Responses to these surveys are included in the digital appendix of this report. Clergy and Staff Participants Marilyn Baldwin Associate Priest Brenda Hoffman Deacon St. Clement s Saint Paul, MN St. Luke s Hastings, MN St. Mary s Catholic Stillwater, MN St. Mary s Episcopal Saint Paul, MN Nancy Whipkey Director of Music Ruth Meyer Asst. Director of Music Mindy Boynton Youth Ministry Marie Goebel Office Administration Edmund Farnham Custodian 15 highlighting key focus areas for each User Group. St. Andrew s Duluth, MN Visioning and Master Plan Draft St. Mary s Alexandria, MN St. Christopher s Roseville, MN St. Anne s Sunfish Lake, MN Visioning and Master Plan Draft

11 Community Engagement Plan Community Engagement Plan Congregation Questionnaire Question 1 What brings you to Ascension for worship on Sunday mornings? What changes Congregation Questionnaire Question 3 What aspects of your current worship spaces do you like the most? The least? to the space would better enhance your worship experience and aid in more meaningful engagement? The people and community are the primary drivers to bring people to Church on Sunday mornings. Members are aware of issues to address; there is a hesitancy to change but acknowledgment of the need. The historic treasure of the building and architecture should be maintained. Members love the space, words cloud diagram The congregation truly appreciates their historic worship space - the windows, historic feel, and woodwork area amongst the most favored. Areas that are least like are the lighting, sight lines, acoustics, and lack of flexibility. words diagram history, and community of Ascension. Question 2 What values and priorities are most important to you in the worship spaces? Question 4 What makes a welcoming worship atmosphere? Describe what the character, image, appearance, etc. should be in the worship spaces. The sense of space to each individual is important and relates to the physical space, the feeling of the space, and the community. Accessibility and acoustics are among the main concerns for the space. words cloud diagram The most important elements to a welcoming atmosphere relate to the people and having a space that is accessible to all individuals. The traditional liturgy, clean, well-kept space and bright facility were highlighted as creating a welcoming atmosphere. words diagram 17 Visioning and Master Plan Draft Visioning and Master Plan Draft

12 Community Engagement Plan Community Engagement Plan Congregation Questionnaire Question 5 Which historical aspects of the building and worship space are of greatest value Congregation Questionnaire Question 7 What about the current lighting in the space enhances and/or limits your wor- and importance to you? ship experience? What changes or modifications would you like to see in the future? Overall, comments were to preserve the beautiful interior, maintain traditional character, and restore existing pews. The stained glass windows are a highly valued historic feature. words cloud diagram Comments were split on the need to change lighting. Factors for changing it included environmental responsibility and functionality. Many comments noted the buzz from the lights and the desire to use a hearing loop system to improve acoustics. words diagram Question 6 Is flexibility in the worship space of value to you? What types of special Question 8 What about the worship spaces enhances or detracts from the musical programs could use the space now and in the future? How important is it to experience? What changes would better support the music at Ascension? have visible community space at Ascension? The congregation was divided with whether or not flexibility was important. Overall, there was consensus that the sanctuary needs to stay a church first and foremost. Several comments discussed that Ascension had other flexible areas and that the worship space should be preserved as is. There was general acknowledgment of the ability to have other events would require greater flexibility in seating and space use. 19 words cloud diagram Visioning and Master Plan Draft The lack of space and flexibility were the most common recurring responses. It was suggested to have the choir facing the congregation. Many people addressed the sight lines in relation to the musicians. words diagram Visioning and Master Plan Draft

13 Community Engagement Plan Community Engagement Plan Congregation Questionnaire Question 9 What do you like and dislike about the technology in the worship space? What Congregation Questionnaire Question 11 What supports or limits the circulation flow in the worship spaces, entries, and technology resources would better aid the worship environment? exits? What are current barriers and what would better aid your worship experience? Hearing loop and improving overall acoustics were the most common responses. Technology that is discretely integrated may be acceptable. Screens and projections were equally suggested and perceived as non-acceptable for the historic space. words cloud diagram The accessibility to communion is a barrier. The lack of space at the narthex is also difficult for people to maneuver. words diagram Question 10 What do you like and dislike about the seating in the worship space? How does Question 12 Please make other comments regarding long-term needs and long-term visions the current seating affect the historical nature and flexibility of the space? for the worship spaces at Ascension Episcopal Church. (This is a catch-all What values of seating options are most important to the worship spaces at question.) You may take the liberty of responding to the question or adding any Ascension? The majority of responses requested to leave the pews. The need to restore them was acknowledged. Many people were open to the idea of rearranging pews or removing some to allow for more room with the altar/chancel. The sense of church should not be lost with any change to seating. words cloud diagram additional comments. There are several members looking to move forward to ensure that Ascension stays relevant. There is a general sense that the historic treasure of the church should be maintained. Members are aware of issues to address; there is a hesitancy to change but acknowledgment of the need. words diagram 21 Visioning and Master Plan Draft Visioning and Master Plan Draft

14 History and Preservation History and Preservation Time-line The following time-line reflects general dates for the Episcopal Church of the Ascension. This does not represent a comprehensive history of the building. It captures significant dates in the congregation s history as revealed in the general Master Planning conversations First Episcopal Service 1846 Regular Services 1851 Construction began on the original Ascension Church on 2nd St., North of the Lowell Inn 1873 Cornerstone laid at current site of 3rd Street 1887 Original Ascension Church struck by lighting and burned down 1888 Current red brick Mid-Victorian Ascension Church constructed 1925 Parish Hall constructed 1950 s Under-croft and basement of the parish hall were remodeled. Parish hall remodeled and kitchen upgraded. Margaret Rivers Chapel added Office Wing constructed 1972 Parish Hall remodeled Renovation of lower level creating classrooms 1985 Dobson pipe organ installed 1986 Major restoration of the church 2001 Renovation to parish hall, classrooms, landscaping and addition of elevator 2013 Stained glass window restoration Original Ascension Church, cornerstone laid May 29, 1851 Sketch by Miss Lee Maunsell Published in Centennial Observance, July 7, Commissioned Visioning and Master Plan Historic Value Visioning and Master Plan Draft Many responses to the Community Engagement Survey highlighted the historic sanctuary as a valued asset and significant feature of worship and the building. Although minor modifications have been made since the church was originally constructed in 1887, many of the sanctuary s significant architectural features remain in good condition. The primary character defining and aesthetic traits of the sanctuary are: Woodwork including: beams, window and door trim, alter, trim along ceiling and chancel woodwork Stained Glass Windows (Tiffany) Furniture: wood pews Plaster walls / ceiling Layout: nave, chancel, altar procession Over the years, these modifications have been made to improve worship and congregational fellowship. Alterations to the historic layout of the church permit a direct path between worship in the sanctuary and secondary church functions: fellowship hall, classrooms, chapel, library, and church offices. Changes to the chancel bring the congregation closer to the alter for communion. The Episcopal Church of the Ascension has set two precedents for their building: 1. The church s stewardship and maintenance of the building has preserved many historic materials and historic integrity of the building. 2. Within the history of the church, the nave has been modified to best suit the needs of congregational liturgy and fellowship. The challenge for the current congregation is to discern whether or not to modify significant elements within the sanctuary. Secretary of Interior s Standards for Rehabilitation Preservation: retaining the existing historic building as it is including modifications that have been made since the building was originally constructed with an understanding that the modifications are part of the history of the building. Rehabilitation: Maintain significant historic features, but permitting changes that maintain the use of a historic building Restoration: returning a building to a defined period of significance, removing elements not dated to the period of significance, repainting to match historic colors, etc. Reconstruction: Rebuilding lost historic elements based on documentation Visioning and Master Plan Draft

15 Visioning and Master Plan Visioning and Master Plan Concept One - Minimal Intervention Concept One - Minimal Intervention Summary Concept One Updated Lighting at Altar, Chancel and Nave Updated Hearing Loop System New mixed flooring at Nave and Narthex Existing 22 full pews and 2 half pews to be restored as required, Seating for 230 to remain Concept Two - Medium Intervention Summary Concept One (Included) Updated Lighting at Altar, Chancel and Nave Updated Hearing Loop System New mixed flooring at Nave and Narthex Concept Two Wider Center Isle Modified Pew Seating for 198 New Choir Seating for 30 Expanded & Reconfigured Chancel with Accessible Ramp Relocated Communion Rails Relocated Choir Chancel remains at 3 steps above Nave Seating Concept One Approximate Estimate$ Concept Two Approximate Estimate$$ 25 Visioning and Master Plan Draft Visioning and Master Plan Draft

16 Visioning and Master Plan Visioning and Master Plan Concept Three - Maximum Intervention Concept Three Approximate Estimate$$$$$$ 27 Summary Concept One (Included) Updated Lighting at Altar, Chancel and Nave Updated Hearing Loop System New mixed flooring at Nave and Narthex Pew Restoration as Required Concept Two (Included) Wider Center Isle Modified Nave Seating New Choir Seating - 30 Expanded & Reconfigured Chancel with Accessible Ramp Relocated Communion Rails Relocated Choir Chancel remains at 3 steps above Nave Seating Concept Three New Addition for interior circulation from Narthex to Gallery Accessible Ramp to maintain accessible entry from north side driveway parking Expanded addition option for internal stair to basement. Expanded Gallery Next Steps Visioning and Master Plan Draft Kodet Architectural Group would like to thank the Ascension Visioning Team for their mindful work in developing this Visioning and Master Plan. We would also like to thank the clergy, staff, Discovery team and many congregation members who extended their thoughts on how to create better facilities. This Visioning and Master plan presents information from which to move forward to better understand the common values of the congregation and to engage in changes as necessary to improve the existing church while preserving its historic qualities. Next steps include, first and foremost, additional conversations and reflections amongst the Ascension community to further understand the concepts presented and align values towards a chosen direction for the church. Kodet looks forward to working with you in the future and recommends a Pre-Design study as a possible next step. This type of study brings together architects along with mechanical, electrical, and structural engineering consultants to develop a concept above the level presented here. It offers time to conduct further studies of the existing conditions and to dig deeper into the design solution, providing the information required for initial cost estimates. Again, thank you for your time and efforts in working with We very much appreciated working with such an engaged congregation and look forward to working with you in the future. Resources The following are professional resources utilized as references for this study that are available to Ascension for further discussion should the church require it. Dobson Pipe Organ Builders, Ltd. 200 N. Illinois St. Lake City, Iowa Contact: Lynn Dobson ldobson@dobsonorgan.com The Gale Family Library Minnesota History Center 345 W. Kellogg Blvd. St. Paul, MN Phone: Sauder Worship Seating 930 W. Barre Rd. PO Box 230 Archbold, OH Regional Contact: John Baker, St. Paul Fabricating & Decorating Company (Pew restoration and fabrication) 1750 Thomas Avenue St. Paul, MN Phone: Contact: Ken Brooks Visioning and Master Plan Draft

17

St. Vincent Martyr Church, Madison, NJ

St. Vincent Martyr Church, Madison, NJ Design Vision for St. Vincent Martyr Church, Madison, NJ JAMES HUNDT LITURGICAL DESIGN CONSULTANT 426 State Street, 3 rd Floor Schenectady, New York (518) 372-3655 THE EXISTING SPACE The current worship

More information

All Saints-by-the-Sea Episcopal Church Sanctuary Preservation and Readiness Project Summary of Questions from the October 23, 2016 Town Hall Meeting

All Saints-by-the-Sea Episcopal Church Sanctuary Preservation and Readiness Project Summary of Questions from the October 23, 2016 Town Hall Meeting All Saints-by-the-Sea Episcopal Church Sanctuary Preservation and Readiness Project Summary of Questions from the October 23, 2016 Town Hall Meeting An extensive Question and Answer session took place

More information

Since 1941, University United Methodist Church has been a presence in the LSU community and surrounding areas.

Since 1941, University United Methodist Church has been a presence in the LSU community and surrounding areas. Since 1941, University United Methodist Church has been a presence in the LSU community and surrounding areas. Our buildings are beautiful and also old. Maintaining our historic structures is an endeavor,

More information

Prayer. Enrichment. Preserving Yesterday, Celebrating Tomorrow

Prayer. Enrichment. Preserving Yesterday, Celebrating Tomorrow Strength Grow Share Learn Commitment Together Community Prayer Enrichment Preserve Fellowship Preserving Yesterday, Celebrating Tomorrow A Message from Fr. Rick Dear Parishioners of St. Peter Parish, I

More information

Joseph. Nativity. This January issue. parish. of the bvm parish. A Letter from Our Pastor Our St. Joseph Church Enhancement Project.

Joseph. Nativity. This January issue. parish. of the bvm parish. A Letter from Our Pastor Our St. Joseph Church Enhancement Project. St. Joseph parish Nativity of the bvm parish \ St. Joseph Parish Church Enhancement Receptions for all parishioners: Monday, January 21 1:30 p.m. 7:00 p.m. Tuesday, January 22 7:00 p.m. All receptions

More information

Architect's Feasibility Study High Street Methodist Church, Harpenden. March highstreet.church the church in the high street

Architect's Feasibility Study High Street Methodist Church, Harpenden. March highstreet.church the church in the high street Architect's Feasibility Study High Street Methodist Church, Harpenden March 2017 highstreet.church the church in the high street We want your feedback on the suggestions in this feasibility study: We

More information

Building Campaign & Annual Commitment to Parish Life

Building Campaign & Annual Commitment to Parish Life Building Campaign & Annual Commitment to Parish Life Loving God, at this time in the life of our parish, we turn to you with grateful hearts, for what we have, and with grateful anticipation of what is

More information

OUR LADY OF CONSOLATION

OUR LADY OF CONSOLATION OUR LADY OF CONSOLATION PROJECT INTRODUCTION Dear friends, The Master Planning Committee and I are seeking your valuable input on the Master Plan for the Our Lady of Consolation campus! Your insight and

More information

Dear brothers and sisters in Christ,

Dear brothers and sisters in Christ, Dear brothers and sisters in Christ, Whenever we think of the term church building, we should always think of building as a verb as well as a noun, for the building of a church is much more than just the

More information

CHURCH PROGRAMMING MEETING 1 - SMALL GROUP DISCUSSION REPORT

CHURCH PROGRAMMING MEETING 1 - SMALL GROUP DISCUSSION REPORT CHURCH PROGRAMMING MEETING 1 - SMALL GROUP DISCUSSION REPORT Please consider the following programmatic statements. Do you agree or disagree? Please state WHY. 1. The historic architectural detail of the

More information

(A) Building for Evangelism

(A) Building for Evangelism (A) Building for Evangelism This is amazing. I can t believe this is in Salina. I ve always wondered what this place looked like inside. Every time I open the door of the Cathedral for someone new, I hear

More information

Guidelines on the Building and Restoration of Church Edifices

Guidelines on the Building and Restoration of Church Edifices Guidelines on the Building and Restoration of Church Edifices A. Introduction In the Catholic Church, the Bishop is the moderator, promoter and custodian of the whole liturgical life of the Church committed

More information

Choosing a Liturgical Consultant

Choosing a Liturgical Consultant Choosing a Liturgical Consultant Federation of Diocesan Liturgical Commissions Choosing a Liturgical Consultant An evaluation workbook to assist parishes hiring a consultant for liturgical space Liturgical

More information

OUR LADY OF THE ROCKIES

OUR LADY OF THE ROCKIES OUR LADY OF THE ROCKIES CANMORE, ALBERTA ron boruk architect ltd. DISTINCTIVE ELEMENTS OF CATHOLIC CHURCH ARCHITECTURE DISTINCTIVE ELEMENTS OF CATHOLIC CHURCH ARCHITECTURE House of God to serve and to

More information

Guidance Note Statements of Significance and Statements of Needs Major Projects

Guidance Note Statements of Significance and Statements of Needs Major Projects Guidance Note Statements of Significance and Statements of Needs Major Projects This form should be used for major complex projects, i.e. the type of project which would normally require the compilation

More information

MISSION. A BRIEF HISTORY of ST. FRANCIS

MISSION. A BRIEF HISTORY of ST. FRANCIS TENTATIVE CASE STATEMENT Gifts Essential Chart This chart illustrates the size and number of gifts necessary for a successful $1,525,000 capital campaign. Size of Gift $100,000 $75,000 $50,000 $25,000

More information

Report of the Sanctuary Renewal Taskforce. Trinity Evangelical Lutheran Church Santa Barbara, CA

Report of the Sanctuary Renewal Taskforce. Trinity Evangelical Lutheran Church Santa Barbara, CA Report of the Sanctuary Renewal Taskforce Trinity Evangelical Lutheran Church Santa Barbara, CA Taskforce Members Pastor Truls, Dennis Lewis, Ed Lenvik, Susan Malde, Linda Vogel, Keith Nolan, Sarah Kreitzer,

More information

TRINITY CHURCH IN 1816

TRINITY CHURCH IN 1816 TRINITY CHURCH IN 1816 TRINITY S Big Dig In May 2009, Trinity Church began to prepare for an exciting construction project that provided a much-needed elevator to a renovated undercroft, a beautiful columbarium,

More information

Our Parish Strategic Plan: Updated on October 3, 2018

Our Parish Strategic Plan: Updated on October 3, 2018 Our Parish Strategic Plan: Updated on October 3, 2018 Introduction Thankful for the past, and hopeful for the future, we make the most of present opportunities! o After retiring the loan for our parish

More information

Renewing and Restoring Our Church. Restoration Committee Report

Renewing and Restoring Our Church. Restoration Committee Report St. Boniface Martyr Roman Catholic Church Sea Cliff, NY Renewing and Restoring Our Church Restoration Committee Report After being rescheduled for bad weather and holidays, the Restoration Committee, an

More information

The Campaign for. Nassau Church

The Campaign for. Nassau Church 1766 1784 1813 1836 1988 2012 The Campaign for Nassau Church The Campaign for Nassau Church As a congregation, we will raise $5 Million in the coming months, in order to fund Phase I implementation of

More information

Living Savior Lutheran Church

Living Savior Lutheran Church Living Savior Lutheran Church Church Expansion Project October 2016 Living Today for Eternity So the churches were strengthened in the faith, and they increased in numbers daily. Acts 16:5 Living Savior

More information

Guidance Note Statements of Significance and Statements of Needs

Guidance Note Statements of Significance and Statements of Needs Guidance Note Statements of Significance and Statements of Needs This form should be used for all projects other than very complex ones. For major complex projects an expanded version of this form is likely

More information

RENEWED JOY. renewed vessels.

RENEWED JOY. renewed vessels. RENEWED JOY. renewed vessels. CENTRAL S HISTORY God called a group of visionary leaders to found Central Lutheran Church in 1919. These founders responded to God s call to begin a congregation so that

More information

Memorial Gift Catalog

Memorial Gift Catalog Memorial Gift Catalog This Catalog contains many opportunities for our parishioners to honor a person, group or occasion with an enduring gift to our St. Andrew Church and parish family. We will continue

More information

I. CALL MEETING TO ORDER AND ROLL CALL

I. CALL MEETING TO ORDER AND ROLL CALL CITY OF SARASOTA MINUTES OF THE REGULAR MEETING OF THE HISTORIC PRESERVATION BOARD Note: The City s Website address is sarasotagov.com. Select Videos on Demand from the Main Web Page to view agendas, videos

More information

...a Time to Build...

...a Time to Build... Ecclesiastes 3:3 A Campaign to Restore & Expand Holy Cross Church Holy Cross Parish Rumson, New Jersey HOLY_CROSS_TIME_TO_CHANGE_2.indd 1 12/21/11 11:05:18 AM Our Mission Parishioners of Holy Cross take

More information

CHURCH OF ST THOMAS MORE INTERIOR DESIGN TEAM Minutes of the Meeting of May 12, 2009

CHURCH OF ST THOMAS MORE INTERIOR DESIGN TEAM Minutes of the Meeting of May 12, 2009 CHURCH OF ST THOMAS MORE INTERIOR DESIGN TEAM Minutes of the Meeting of May 12, 2009 Present: Father Michael Ratajczak, Robert Habiger, Phil Goscienski, Pat Goscienski, Douglas Lynn, Sondra Parks, Charlene

More information

Title: Stairway to Heaven: A closer look at the inclusiveness and accessibility of the United Methodist Church

Title: Stairway to Heaven: A closer look at the inclusiveness and accessibility of the United Methodist Church About the Author: Author: Brooke McClure Title: Stairway to Heaven: A closer look at the inclusiveness and accessibility of the United Methodist Church Keywords: United Methodist Church, Wesley, disability,

More information

INTRODUCTION SITE. First Baptist Church of Guilford is the 15 th oldest church in Columbia, Maryland. First Baptist is one of

INTRODUCTION SITE. First Baptist Church of Guilford is the 15 th oldest church in Columbia, Maryland. First Baptist is one of INTRODUCTION SITE First Baptist Church of Guilford is the 15 th oldest church in Columbia, Maryland. First Baptist is one of 1 fourteen churches in Howard County that dates back to the late 1800 s and

More information

The. Church of the Good Shepherd. Pitman, N.J. / Parish Profile

The. Church of the Good Shepherd. Pitman, N.J. / Parish Profile 2015 Transition Process Goodshepherdpitman@gmail.com The Welcome to our faith community! Church of the Good Shepherd Pitman, N.J. / Parish Profile A Prayer for Discernment Almighty and everliving God,

More information

Holy Apostles began as a

Holy Apostles began as a TENTATIVE CASE STATEMENT Church of the Holy Apostles Collierville, TN Leadership The Rev. John P. Leach Rector The Rev. Susan K. Crawford Priest Associate Steering Team Susan Kenny Tiffany Siegel Master

More information

Redeemer Missionary Baptist Church: Minneapolis, Minnesota Case Study By Maianne Preble Fall 2009

Redeemer Missionary Baptist Church: Minneapolis, Minnesota Case Study By Maianne Preble Fall 2009 Redeemer Missionary Baptist Church: Minneapolis, Minnesota Case Study By Maianne Preble Fall 2009 1. Intro a. Building Typology Community houses of worship have long played a major, yet quiet, role in

More information

+Saints Constantine and Helen Greek Orthodox Church Strategic Plan 2009 I 2010 I 2011 I 2012 I 2013

+Saints Constantine and Helen Greek Orthodox Church Strategic Plan 2009 I 2010 I 2011 I 2012 I 2013 +Saints Constantine and Helen Greek Orthodox Church Strategic Plan 2009 I 2010 I 2011 I 2012 I 2013 Mission Statement The mission of Saints Constantine & Helen Greek Orthodox Church in Newport News, Virginia

More information

Report to Church Conference

Report to Church Conference Sanctuary Study Committee Report to Church Conference Los Altos United Methodist Church March 6, 2016 (d) INTRODUCTION Contents Formation of Sanctuary Study Committee 3 Book of Discipline Process...3 Activities

More information

Heritage Evaluation of the North Bay Synagogue Municipal Heritage Committee, North Bay Page 1 of 9

Heritage Evaluation of the North Bay Synagogue Municipal Heritage Committee, North Bay Page 1 of 9 Municipal Heritage Committee, North Bay Page 1 of 9 1. Property Description 1.1 Basic Description: The Sons of Jacob Synagogue is found at 302 McIntyre Street West, at the intersection of McIntyre Street

More information

First Parish Church Meetinghouse: Past and Plans

First Parish Church Meetinghouse: Past and Plans First Parish Congregational Church United Church of Christ PO Box 114, 47 East Derry Road East Derry, NH 03041 (603) 434-0628 www.fpc-ucc.org BACKGROUND First Parish Church Meetinghouse: Past and Plans

More information

Terms, Definitions and Other Pertinent Information

Terms, Definitions and Other Pertinent Information What s the Latest? A Publication of St. John Paul II Parish, Sellersburg, Indiana Volume 1, Issue 1 February 2016 St. John Paul II Parish Master Plan Terms, Definitions and Other Pertinent Information

More information

Liturgical Customary

Liturgical Customary Liturgical Customary Liber Ordinarius Pentecost 2015 There is more than one right way of working in a liturgical space. Yet the liturgy is usually enhanced by some consistency and a sense of expectation.

More information

Determining Meetinghouse Adequacy

Determining Meetinghouse Adequacy Determining Meetinghouse Adequacy Contents Introduction... 2 Inspect and Rate the Building... 2 Review Meetinghouse Usage... 2 Evaluate Options... 3 Short-Term vs. Long-Term Needs... 3 Identifying Solutions...

More information

Highlights Holy Family St. Thomas Aquinas, Brooklyn, New York

Highlights Holy Family St. Thomas Aquinas, Brooklyn, New York Highlights 2014-2015 Holy Family St. Thomas Aquinas, Brooklyn, New York After we completed the exterior restoration of St. Thomas Aquinas, interior restoration work was scheduled in phases over a four

More information

An Exciting Opportunity. A Dynamic Community

An Exciting Opportunity. A Dynamic Community Renewing Our Community Campaign 2017 An Exciting Opportunity Renewal... from time to time, we all feel the need for it. Sometimes it is a matter of renewing ourselves physically or spiritually. Stress,

More information

St. Joseph Elementary & Preparatory School State of the Schools

St. Joseph Elementary & Preparatory School State of the Schools St. Joseph Elementary & Preparatory School State of the Schools 2015-16 Purpose of Catholic Schools Not so our children can get better jobs. Not so our children can make more money. Not so our children

More information

Call to Community Worship Fellowship Stewardship

Call to Community Worship Fellowship Stewardship TENTATIVE CASE STATEMENT CHURCH OF ST. ANDREW EPISCOPAL Marblehead, MA Leadership The Reverend C.Clyde Elledge Rector Vestry Steve Hahn Senior Warden Nat Wysor Junior Warden John Howard Treasurer Glenn

More information

You are invited to join Beth David in an experiment

You are invited to join Beth David in an experiment You are invited to join Beth David in an experiment The Board of Directors, and the Ritual Committee have approved a trial period of modified seating in the Beth David sanctuary with all the men on one

More information

The Cathedral Community

The Cathedral Community The Cathedral Community Rochester, New York Building a Solid Future in Hope Capital Campaign Building a Solid Future in Hope Campaign Prayer Gracious God, through Your Holy Spirit, You continue to bless

More information

CHURCH OF ST THOMAS MORE Interior Design Team Minutes of Meeting of August 20, 2008

CHURCH OF ST THOMAS MORE Interior Design Team Minutes of Meeting of August 20, 2008 CHURCH OF ST THOMAS MORE Interior Design Team Minutes of Meeting of August 20, 2008 Attending: Father Mike Ratajczak, Phil Goscienski, Pat Goscienski, Mary Castle, Sondra Parks, Diana Diaz, Mario Diaz,

More information

Grace Episcopal Church Capital Campaign

Grace Episcopal Church Capital Campaign Grace Episcopal Church Capital Campaign Grace Episcopal Church 160 High Street Medford, MA 02155 www.gracemedford.org Dear Friends, Grace Episcopal Church is a beacon of hope and faith to our members and

More information

Trinity Episcopal Church Fishkill, NY Minutes of Vestry Meeting on May 20, 2014

Trinity Episcopal Church Fishkill, NY Minutes of Vestry Meeting on May 20, 2014 Trinity Episcopal Church Fishkill, NY 12524 Minutes of Vestry Meeting on May 20, 2014 The Rev. Jean Campbell called the meeting to order at 7 p.m. Opening prayers were offered. Present: The Rev. Jean Campbell;

More information

Dunscore Parish Church

Dunscore Parish Church Dunscore Parish Church Registered Scottish Charity SC016060. Congregation Number 080454. Bogrie, Dunscore DG2 0UT. 01387 820480. Janet Johnstone Secretary to Dunscore Community Council. 11 April 2016 Dear

More information

2016 Parish Survey Results

2016 Parish Survey Results 1 St. Joseph Catholic Church Richardson, Texas 2016 Parish Survey Results Narrative Summary Report Overview Executive Summary Narrative Summary Report Appendix A: Parish Demographic Survey Results Appendix

More information

New Building Proposal

New Building Proposal O Fallon First United Methodist Church. New Building Proposal Church Conference October 29, 2018 CONTENTS 1 Letter from Our Pastor... 2 Our Vision... 3 Our Proposal... 5 The Motion... 8 Frequently Asked

More information

Criteria for Designation Saint James African Methodist Episcopal (AME) Church meets criterion 1 as a landmark under section 599.210 of the Heritage Preservation Regulations. Further investigation may demonstrate

More information

Property Board Policy For Use of Church Facilities and Equipment

Property Board Policy For Use of Church Facilities and Equipment Property Board Policy For Use of Church Facilities and Equipment The Property Board of St. Paul Lutheran Church, New Braunfels, Texas (SPLC), has created these general guidelines to manage church property

More information

Hospitality Team Handbook Mt Zion Lutheran Church

Hospitality Team Handbook Mt Zion Lutheran Church Hospitality Team Handbook Mt Zion Lutheran Church Maintained by the Hospitality Team Coordinator and Pastor October 6, 2012 Table of Contents GENERAL. 3 HOSPITALITY TEAM MINISTRY OVERVIEW 3 MNISTRY TEAM

More information

ALL SAINTS ANGLICAN CHURCH, PETERBOROUGH

ALL SAINTS ANGLICAN CHURCH, PETERBOROUGH Parish discussion regarding the Anglican-Lutheran Churches in Peterborough held on October 15, 2017 Introduction Following a lengthy process of working to discern the needs of our Anglican-Lutheran congregations

More information

Building Together. In Faith. St. Teresa of Avila Catholic Church. Rendering. In Support Of Our Plans To Construct a New Worship Space

Building Together. In Faith. St. Teresa of Avila Catholic Church. Rendering. In Support Of Our Plans To Construct a New Worship Space Building Together In Faith St. Teresa of Avila Catholic Church Rendering In Support Of Our Plans To Construct a New Worship Space St. Teresa of Avila Catholic Church Grovetown, GA Introduction St. Teresa

More information

Pre-Capital Campaign Feasibility Study Report

Pre-Capital Campaign Feasibility Study Report Pre-Capital Campaign Feasibility Study Report for Community United Methodist Church Naperville, Illinois June 2014 Prepared by: John V. Clark Tim McKearn Donna Lund June 2014 Community United Methodist

More information

Adas Torah - an Orthodox Jewish synagogue - seeks to relocate from the Beverlywood to Pico Robertson area. Adaptive reuse of the vacant Victory

Adas Torah - an Orthodox Jewish synagogue - seeks to relocate from the Beverlywood to Pico Robertson area. Adaptive reuse of the vacant Victory Adas Torah - an Orthodox Jewish synagogue - seeks to relocate from the Beverlywood to Pico Robertson area. Adaptive reuse of the vacant Victory Furniture building significant façade remodel, interior floor

More information

PHOTOGRAPH RECORD ST. JOSEPH'S CATHOLIC CHURCH Bullion Street, Mariposa, CA August 2012

PHOTOGRAPH RECORD ST. JOSEPH'S CATHOLIC CHURCH Bullion Street, Mariposa, CA August 2012 PHOTOGRAPH RECORD ST. JOSEPH'S CATHOLIC CHURCH 4983-4985 Bullion Street, Mariposa, CA August 2012 Photograph 1: View of St. Joseph's Catholic Church, circa 1864. This is the oldest known image of the church

More information

Comprehensive Fund Appeal Questions & Answers

Comprehensive Fund Appeal Questions & Answers Comprehensive Fund Appeal Questions & Answers St. Matthew s Ev. Lutheran Church What is the Grounded in Faith~ Growing to Serve appeal? Together, we remain united around our mission to fulfill the Great

More information

Summer Revised Fall 2012 & 2013 (Revisions in italics)

Summer Revised Fall 2012 & 2013 (Revisions in italics) Long Range Plan Summer 2011 Revised Fall 2012 & 2013 (Revisions in italics) St. Raphael the Archangel Parish is a diverse community of Catholic believers called by baptism to share in the Christian mission

More information

Capital Gifts Initiative Generation to Generation. Holy Trinity Episcopal Church

Capital Gifts Initiative Generation to Generation. Holy Trinity Episcopal Church Capital Gifts Initiative Generation to Generation Holy Trinity Episcopal Church Dear Friends in Christ, We are part of a blessed and noble heritage. Founded as St. Barnabas in 1871, and established as

More information

Our Faithful Journey

Our Faithful Journey Our Faithful Journey Feeding the Community, Body, Mind and Spirit North Olmsted United Methodist Church in 2025 Our Blueprint for Community Ministry Dear Members and Friends of NOUMC, In September 2016,

More information

GROUP MEMBERS: BAR 423: INTERIOR ARCHITECTURE 3 GROUP 6 PRESENTATION: B02/0760/2010 B02/35582/2010 B02/0777/2010 B02/37539/2010

GROUP MEMBERS: BAR 423: INTERIOR ARCHITECTURE 3 GROUP 6 PRESENTATION: B02/0760/2010 B02/35582/2010 B02/0777/2010 B02/37539/2010 BAR 423: INTERIOR ARCHITECTURE 3 GROUP 6 PRESENTATION: SPORTS CAFETERIA AND TERRACE ADULT PUB/BAR DISCOTHEQUE RELIGIOUS SANCTUARY GROUP MEMBERS: KARIUKI CAROLINE WANGUI: MUTERO NJERI: OBILO YURI OBARA:

More information

Centenary United Methodist Church

Centenary United Methodist Church Centenary United Methodist Church Mankato, Minnesota January 13-15, 2017 The Missional Church Consultation Initiative (MCCI) Team would like to thank Pastor Michelle Hargrave and the leadership of Centenary

More information

Living History. NEWSLETTER October New doors for Community Building

Living History. NEWSLETTER October New doors for Community Building Living History. NEWSLETTER October 2010. New doors for Community Building The initial cost of the doors is approximately 5,500. The principal grants were from "The Croft Trust" and "The Landfill Tax" through

More information

Heritage Register - Building

Heritage Register - Building 2414 Columbia Avenue - Sacred Heart Catholic Church Sacred Heart Catholic Church 2009 Heritage Register - Building 1) Historical Name: Sacred Heart Catholic Church 2) Common Name: 3) Address: 2414 Columbia

More information

Ushers & Greeters Guide to Everything. About Everything. June 9

Ushers & Greeters Guide to Everything. About Everything. June 9 Ushers & Greeters Guide to Everything June 9 2013 About Everything Use this manual as a reference guide. Remember that although there are a lot of ins-and-outs to helping a service run smoothly your most

More information

St. Paul s Episcopal Church Kansas City, Missouri

St. Paul s Episcopal Church Kansas City, Missouri Feasibility Study Report for St. Paul s Episcopal Church Kansas City, Missouri September 2013 Building a Culture of Generosity 3 West 63 rd Street, Kansas City, MO 64113 Denis Greene, President 816/560-3641

More information

Feasibility Study Report. St. Paul of the Cross Catholic Church Atlanta, Georgia

Feasibility Study Report. St. Paul of the Cross Catholic Church Atlanta, Georgia Feasibility Study Report for St. Paul of the Cross Catholic Church Atlanta, Georgia March 2017 Building a Culture of Generosity Building a Culture of Generosity Feasibility Study Report for St. Paul of

More information

St. Pius X Catholic Church 122 West 400 North Moab, Utah Parish Council Meeting #2 September 19, :00 p.m.

St. Pius X Catholic Church 122 West 400 North Moab, Utah Parish Council Meeting #2 September 19, :00 p.m. St. Pius X Catholic Church 122 West 400 North Moab, Utah 84532-0357 Parish Council Meeting #2 September 19, 2016-6:00 p.m. 1. Opening Prayer Father Bill opened this Parish Council Meeting #2 with a reading

More information

Stairway to Heaven: people. However, in some churches like Wesley United Methodist Church, the altar can be a

Stairway to Heaven: people. However, in some churches like Wesley United Methodist Church, the altar can be a Stairway to Heaven: A closer look at the inclusiveness and accessibility of the United Methodist Church Socially, the United Methodist Church as a whole is a welcoming organization to all people. However,

More information

CANDLEWOOD elementary school. campus needs Bond Proposal The above listed campus is programmed to receive the following items:

CANDLEWOOD elementary school. campus needs Bond Proposal The above listed campus is programmed to receive the following items: CANDLEWOOD elementary school Years of Previous work (since 1988) 1988 009 8.011 94,04 1 45 Replace Panel, Upgrade Fire Alarm System, Upgrade Smoke & Duct Detectors - Fall 00 Replace Sewer Lines under Building

More information

Sons of Abraham Synagogue

Sons of Abraham Synagogue HISTORIC RESOURCES 2013 City of Medicine Hat Sons of Abraham Synagogue Date of Construction 1912 Address 530-5 (Ottawa) Street SE Original Owner Elijah L. Becker Architect Elijah L. Becker Contractor Mat

More information

USHERS HANDBOOK. ST. JAMES S EPISCOPAL CHURCH 1205 W. Franklin Street Richmond, VA (804)

USHERS HANDBOOK. ST. JAMES S EPISCOPAL CHURCH 1205 W. Franklin Street Richmond, VA (804) USHERS HANDBOOK ST. JAMES S EPISCOPAL CHURCH 1205 W. Franklin Street Richmond, VA 23220 (804) 355-1779 www.doers.org Dear Friends, Thank you for your willingness to take part in this important ministry.

More information

St. John Lutheran Church Boards, Committee & Group Questionnaire

St. John Lutheran Church Boards, Committee & Group Questionnaire St. John Lutheran Church Boards, Committee & Group Questionnaire 2018.12.11 General Facility Questions 1. List 3 Key functions the Current Church Facility does not provide adequate accommodation for. (e.g.

More information

St Paul s Lutheran Church, Jerome Parish 4109 Jerome Rd Edinburg, VA 22824

St Paul s Lutheran Church, Jerome Parish 4109 Jerome Rd Edinburg, VA 22824 St Paul s Lutheran Church, Jerome Parish 4109 Jerome Rd Edinburg, VA 22824 A brief History St Paul s congregation of Jerome was organized in 1827 at that time they met in a one room log school house owned

More information

St. Joseph s Church, Toms River Feasibility Study Case for Support

St. Joseph s Church, Toms River Feasibility Study Case for Support St. Joseph s Church, Toms River Feasibility Study Case for Support The Catholic Community of St. Joseph s can trace its origins back to the 1870s when a few people gathered for Mass in private homes celebrated

More information

CHURCH BUILDING REVIEW SURVEY. for St. Anywhere, Tigercross

CHURCH BUILDING REVIEW SURVEY. for St. Anywhere, Tigercross CHURCH BUILDING REVIEW SURVEY for St. Anywhere, Tigercross Parish Number: 443 Listed: Grade II* Built: 1889 Architect: Conservation Area Status: Aldridge & Deacon Date of latest Quinquennial Church Inspection:

More information

Zion Lutheran Church Forward in Faith

Zion Lutheran Church Forward in Faith Zion Lutheran Church Forward in Faith Be strong and courageous and get to work, for the Lord my God is with you. The Lord will not forsake you. Don t be frightened by the size of the task. God will see

More information

Historic District Commission January 22, 2015 City of Hagerstown, Maryland

Historic District Commission January 22, 2015 City of Hagerstown, Maryland Michael Gehr, chair, called the meeting to order at 4:30 p.m. on Thursday, January 22, 2015, in the Conference Room, Fourth Floor, City Hall. A roster of the members of the commission and the technical

More information

Architecture. Richard Upjohn s Church

Architecture. Richard Upjohn s Church Architecture Immediately after organizing St. Mark s Church in 1858, Episcopalians in San Antonio set out to erect a building. No matter that San Antonio was a rowdy frontier outpost reached only by a

More information

ST MARTIN OF TOURS CHURCH, EYNSFORD Diocese of Rochester

ST MARTIN OF TOURS CHURCH, EYNSFORD Diocese of Rochester ST MARTIN OF TOURS CHURCH, EYNSFORD Diocese of Rochester INTRODUCTION St Martin s Church is in the parish of Eynsford in the Darent Valley about seven miles north of Sevenoaks. The village lies within

More information

Opening Reflection Fr. Shaun Eaton. Shaun spoke about some of the principles of an effective team, and led us in prayer.

Opening Reflection Fr. Shaun Eaton. Shaun spoke about some of the principles of an effective team, and led us in prayer. St. John in the Wilderness Church Council Meeting Thurs. March 14, 2019 Present: Sandra Fraser, Peter Langille, Denise Hilary, Brent Anderson. Ron Jackson, Shirley MacKenzie, Janice MacAlpine, Brian Fogg,

More information

Access Statement for Coventry Cathedral

Access Statement for Coventry Cathedral Access Statement for Coventry Cathedral Introduction Coventry Cathedral is situated in the city centre of Coventry. The site includes the second Cathedral (known as the old Cathedral and often referred

More information

Guidelines for Construction Projects and Construction Financing (Parish Faith Communities)

Guidelines for Construction Projects and Construction Financing (Parish Faith Communities) Guidelines for Construction Projects and Construction Financing (Parish Faith Communities) What Steps Need to be Taken to Undertake Construction or Alteration of Real Property? Where to begin: Any construction

More information

ST. MARK S UNITED METHODIST CHURCH SANCTUARY HVAC PROJECT

ST. MARK S UNITED METHODIST CHURCH SANCTUARY HVAC PROJECT ST. MARK S UNITED METHODIST CHURCH SANCTUARY HVAC PROJECT To the Friends of St. Mark s: Michelle Rekitzke, Senior Pastor Did you know that the 1st Sunday worship service in the Sanctuary at St. Mark s

More information

Lord, what do You want to do through me?

Lord, what do You want to do through me? Lord, what do You want to do through me? littleton united methodist church 5894 s datura st littleton, co 80120 A Letter from our Campaign Co-Chairs: Pat Estes and Merv Graham Dear Friends, Among the Commandments

More information

ANNUAL BUDGET MEETING 2018

ANNUAL BUDGET MEETING 2018 ANNUAL BUDGET MEETING 2018 2019 Proposed Ministry Goals & Budget November 11, 2018 Hearts consumed by Christ. As we focus on 2019 and the continuation of our 20/20 Vision priorities, Redeemer s board has

More information

USHER PROCEDURES Berwyn United Methodist Church

USHER PROCEDURES Berwyn United Methodist Church USHER PROCEDURES Berwyn United Methodist Church Revised 8/15/2016 Ushers are an important part of the hospitality ministries of our church. They are the face of our church who provide a warm welcome that

More information

Strategic Plan

Strategic Plan 2017-2022 Strategic Plan Dear Parish Family, With eyes looking to Jesus Christ and hands stretched to heaven, St. Francis of Assisi beheld a vision of our Lord and received the stigmata (see front cover).

More information

SACRISTAN PREPARING THE WAY. A guide for Sacristans at St. Albert the Great Catholic Church

SACRISTAN PREPARING THE WAY. A guide for Sacristans at St. Albert the Great Catholic Church SACRISTAN PREPARING THE WAY A guide for Sacristans at St. Albert the Great Catholic Church Sacristan Preparing the Way A Guide for Sacristans at St. Albert the Great Catholic Church REVISED AND UPDATED

More information

Diocese of Southern Ohio

Diocese of Southern Ohio Approved by: The Rt. Rev Thomas Breidenthal Bishop, Diocese of Southern Ohio Approval Date: 4/08/2017 1. Theological Context The Diocese has adopted this policy in the interest of promoting our common

More information

PIONEER MEMORIAL CHURCH

PIONEER MEMORIAL CHURCH PIONEER MEMORIAL CHURCH NOTE FROM OUR PASTOR Some of the most joyous moments of Scripture were when the people of God rallied to build or rebuild renovate the House of God.... they knelt on the pavement

More information

ST. JOHN S EPISCOPAL CHURCH N. John Young Parkway, Kissimmee, FL

ST. JOHN S EPISCOPAL CHURCH N. John Young Parkway, Kissimmee, FL ST. JOHN S EPISCOPAL CHURCH 1709 N. John Young Parkway, Kissimmee, FL 34741 www.stjohns-ec.com 2 Welcoming all of God s family to grace, hope and healing in the love of Christ. Sharing His love with our

More information

The Language of our Church, space and furnishings (1/3) The Language of our Church, space and furnishings (2/3) From the 2016 Committee:

The Language of our Church, space and furnishings (1/3) The Language of our Church, space and furnishings (2/3) From the 2016 Committee: From the 2016 Committee: The Language of our Church, space and furnishings (1/3) Spaces within the Church Chancel The chancel is the front part of the church from which the service is conducted. The chancel

More information

USHER PROCEDURES Berwyn United Methodist Church

USHER PROCEDURES Berwyn United Methodist Church USHER PROCEDURES Berwyn United Methodist Church Revised 1/9/2019 Ushers are an important part of the hospitality ministries of our church. They are the face of our church who provide a warm welcome that

More information

The Church of the Good Shepherd Long Range Plan 2016

The Church of the Good Shepherd Long Range Plan 2016 The Church of the Good Shepherd Long Range Plan 2016 Page 1 Page 2 A Letter from our Senior Warden Dear Members of the Parish: Change is the New Normal. Just this year, The Church of the Good Shepherd

More information

VESTRY MINUTES 5:30 p.m., Monday, June 26, 2017 St. John s Episcopal Church

VESTRY MINUTES 5:30 p.m., Monday, June 26, 2017 St. John s Episcopal Church 1 VESTRY MINUTES 5:30 p.m., Monday, June 26, 2017 St. John s Episcopal Church Vestry present: Travis Baldwin, Fred Boothe, Matt Brown, Mary Fitzgerald, Ray Lowther, Robin O Brien, Bren Pomponio, Scott

More information